Woodland Camp Update – 05 January 2019

This week the brothers focused on site work around the property.


Trenching has commenced again, and the brothers are working to bring water and gas to the eastern bank of cabins.


A temporary road was built at the northern entrance to the camp to provide access to UKPN (UK Power Network) lorries. UKPN will connect a new electrical service to the camp next week.


Waterproofing paint was applied to the central plant retaining walls. This paint will protect the walls from erosion when they are buried. Scaffolding was also erected around the building to protect the brothers and provide a platform for them to work on.


The brothers have begun to install the electrical wire in the prototype cabin.